Feb 42
Small Units Cook House in what is now BathHouse. 5 Stoves to new design with Circular Draught First Job in Camp.
March 42
Build Kitchen for Officers in Jubilee 3 stoves & Friers c iron around the Building, doors & Generally making place liveable .
April 42
April 42
May – July 42
RAMC. Hospital C/House. 3 Stoves, Water Heater, frier Wok and larger boiler for Veg Cooking this took on & off quite a time as materials were scarce & we were on our own
Nov 42
Dec 42
Jan - Feb 43
Feb 43
Feb 43
Feb 44
Feb 43
19-2-43. urgent work till 6PM.
8-3-43
13-4-43
April 43
12-5-43
June 43
8-6-43
July 43
26-July 43
26 July 43
27 Aug 43
Hospital C/House Repairs & reconstruction of all …….. and Imir, Repairs to roof. Mess in Hosp C/House
23-Sept 43
6-Oct 43
16-Oct 43
22-Oct 43
3-Nov 43
16-Nov 43
8-Dec 43
17-Dec 43
1-4-44 – 2-3-44
17-4-44
21-4-44 – 1-5-44
24-4-44
Start work Jubilee Cook House for Japanese which comprised months of work. Cement being supplied for 6 cookers. Then a small range for the officers.
20-5-44
Draining Jubilee Area by Pipelinesand cutting through the sea wall. This was done twice to obtain satisfaction
6-7-44
20-7-44
30-7-44
14-8-44
28-8-44
29-8-44
20-9-44
27-10-44
2-11-44
5-11-44
8-11-44
While at Jubilee we had also Built Complete Bath House on the style of the Red Cross one in the line. 2 Bath large and 8 ….with separate furnaces this would be about . July and August 1944 all that time was spent at Jubilee. Once we had to go back & make the Bath House Draught Proof
22-4-44
12-12-44
6-1-45 onwards
30-1-45
Making windows at odd times for the lines.
20-2-45
1-1-45
Feb 45
23-2-45
24-2-45
1-4-45
5-4-45
5 to 12-4-45
12-4-45
18 to 27-4-45
28 to 30-4-45
1-5-45
3 to 4-5-45
5-5-45
1-6-45
Rabbit Hutches – Pig Trough and make chicken farm cat proof this combined with shelter approx 1 week for shelters 16 men.
2 to 10-6-45
10 to 14-6-45
18.6.45
23-6-45
1-7-45
14-7-45
18-7-45
21-7-45